Design update and Construction Supervision of Lot-5: Savannah Commodities-Bugolobi-UBC Link (1541m)

MBW Consulting Ltd was awarded this contract to carry out design update and construction supervision of drainage system. The savannah-Bugolobi channel is one of the major secondary storm water drainage channels in Kampala within the Nakivubo catchment. The drainage channel improvement works were aimed at reducing flooding frequency and magnitude in the area by enhancing the channel flow capacity through channel expansion, realignment and lining.

Our Roles:

  • Environmental and social safeguard monitoring and implementation
  • Contract Management and Administration
  • Topographic survey
  • Production of detail drawings
  • Works inspection
  • Cost estimation & cost control
  • Claims & dispute management